Guidelines for
Preparing New Workload Request
Background
As approved by UCOP Budget Office, campus proposals
form the basis for the University's request for State funding for new (added
or reduced) workload for Operations and Maintenance of Plant (OMP). A consolidated
request for all campuses is included in the Regents Budget. Funds for new
workload are ultimately provided from within the budget negotiated with the
Governor, the Department of Finance, and the Legislature. Each year the Budget
Office sets priorities and follows guidelines that support the effective
and efficient management of State OMP support.
Campus proposals are reviewed by the Budget Office to
confirm square footage, occupancy dates, State OMP funding eligibility, and
otherwise clarify project and building level details associated with each
proposal. The Facilities Inventory Guide (FIG) should be referred to for
information on eligibility for OMP funding. Additionally, Budget Office procedures
established in fiscal year 2002-03 and earlier remain in effect.
Guidelines
If
a campus believes an exception to any of the above is merited,
it should submit a request with justification and it will be evaluated
on a case-by-case basis.
|
Administrative Procedures
Complete one Workload
Addition (or Reduction) Request (Form 5-A) form for each new
(or deleted) space request; provide attachments as required.
Gather copies of all required attachments as identified
on the Request form, including:
For all Chancellor-approved projects, submit copy
of signed Capital Improvement Budget (CIB).
For projects not yet in construction, submit copy
of latest project schedule.
For all projects in construction, submit copy of latest
construction schedule as issued by contractor.
For projects at or near completion, submit copy of
Certificate of Beneficial Occupancy, Certificate of Substantial Completion
or Notice of Completion.
Complete the New
Workload Request Summary (Form 5-B) listing all space revisions
requested.
Submit an electronic copy of these documents (via
email attachment) to Coordinator Clifton
Bowenn.
Required attachments should be included (please fax (510) 987-9819 if the documents
cannot be transmitted electronically).
Questions?
Questions should be addressed to Coordinator Clifton
Bowen at (510) 987-9819.
* Assignable Square Feet (asf) is converted by formula to Maintained