State Public Works Board and Dept. of Finance Submittal Guidelines for State Funded Capital Projects

STATE PUBLIC WORKS BOARD and DEPT. of FINANCE
SUBMITTAL GUIDELINES for State Funded Capital Projects
April 6, 1999

The purpose of the following guidelines is to provide information to campus project managers regarding preparation of documentation for submittals of preliminary plans, working drawings, and related items to the State Public Works Board (SPWB) or Department of Finance (DOF) for approval, authorization to proceed to the next phase, and/or release of funds.

While a project manager views a project as the story of bringing together all of the various resources and people required to construct a building on a particular location, the State has a much different perspective.  For a State-funded project the story is almost exclusively concerned with the appropriation of funds and the release and tracking of these funds.  For the project manager, understanding the logic of the State perspective and the constraints it places on the project as a whole can mean the difference between an easy project or a disaster.  UCOP State Capital Program staff have the responsibility of facilitating and bridging the gap between these two very different views of a project.

The University and the campuses need the resources from the State on a continuing basis and are dependent on the support of State staff securing and implementing State appropriations.  Therefore it stands to reason that we should make every effort to understand the logic of the State funding process and see that State concerns and regulations are addressed in both spirit and in detail in the course of project development and delivery.   In this way the University and the campuses can benefit from the continuing maintenance of positive working relationship with the State.

These guidelines attempt to give a broad non-technical overview of the approval and release process and to provide specific operational direction to project managers to assist in making the process as clear and straightforward as possible.  However it is likely that there will be questions as project managers apply these guidelines in their individual projects.  Please feel free to call the UCOP Capital Plan Review Coordinator (Principal Architect James Maguire, 510.987.0776, email: james.maguire@ucop.edu) when questions first arise so that assistance can be provided in a timely manner.
 

General


Required Submittal Components


Detailed Requirements for Submittal Components


Blank Forms

  1. Request for Approval to Proceed or Encumber Funds (Streamlined Processing

SUBMITTALS TO THE SPWB

Not all project submittals go to the SPWB.  A submittal to State Public Works Board (SPWB) is required for:

  • Approval of preliminary plans for all capital projects that have State funds allocated for any phase of a project, unless the budget appropriation explicitly exempts the project.  Even if State funds are only allocated for a portion of the "C" phase, but not "P" or "W", preliminary plans must still be approved by the SPWB prior to requesting Department of Finance (DOF) approval of the working drawings and release of the construction funds.
  • Authorization of agreements required if the State funds are provided through Lease Revenue Bonds.  This includes a resolution for the sale of SPWB Lease Revenue Bonds; approval of a Site Lease, Facility Lease, Construction Agreement, and Equipment Lease and Equipment Agreement as applicable; and approval of interim funding for all Revenue Bond funded projects.  Note - these are usually submitted at the completion of working drawings unless working drawings are also funded with Revenue Bonds.  DOF reviews and approves the working drawings concurrent to the action taken above by the SPWB.
  • Approval of an Augmentation (based on bids) or a Recognized Anticipated Deficit (anticipated augmentation to a project, prior to bid) which results in a request for added State funds over 10% of the project cost or over $50,000, whichever is less, up to 20% of the statutory limit, subsequent to notification by 20-day letter of the Joint Legislative Budget Committee.  Also note that due to funding limitations augmentation requests are made only on an exception basis.
The SPWB meets on a monthly basis.  Items to be submitted must first be reviewed by UCOP before being forwarded to DOF for action and their inclusion in the agenda for the SPWB meeting.  Because of the time required for review and public notice, submissions must be received by UCOP approximately six to seven weeks prior to the applicable SPWB meeting date.  Each year, in December, State Capital Program Development staff at UCOP prepare and distribute a SPWB meeting calendar with deadlines for submission to OP relative to each meeting.  Because of the lead times associated with these meetings, it is important to carefully consider them in the overall project schedule.

SUBMITTALS TO DOF

A submittal to Department of Finance (DOF) is required for: 

  • Approval of bid package (working drawings) and authorization to proceed to bid.
  • Approval to bid the project in separate packages whether concurrently or sequentially.  This approval is usually requested at the working drawing submission.
  • Approval of alternates to be included in the bid package. This is done concurrently with the working drawing submission.
  • Approval to award the construction contract and release the construction funds, based on bids.
  • Approval of an Augmentation (based on bids) or a Recognized Anticipated Deficit (anticipated augmentation to a project, prior to bid) which results in a request for added State funds when under 10% of the project cost or under $50,000, whichever is less.  Note:  This authority was delegated to the DOF by the SPWB and is subject to review each year.  Also note that due to funding limitations augmentation requests are made only on an exception basis.
  • Approval to combine the bids for projects funded by separate appropriations, requested at the working drawings submission.  Note: This was delegated to the DOF by the SPWB and is subject to review each year.
  • Approval to bid a non-State funded project with a State funded project, requested at the time of the approval of working drawings.
Submissions to DOF are made by UCOP on a continuing basis. Once the required documents have been received and reviewed by UCOP the submission is forwarded to DOF for action. Depending on DOF workload, approval is usually returned to UCOP within one to two weeks.  UCOP staff notifies the project manager and forwards the signed approval form.  Transfers of funds and their notifications follow by separate correspondence. 

STREAMLINED PROCESSING

The Budget Act appropriation for a specific project phase of work may include provisions that, by agreement with the Department of Finance, effectively delegate responsibility for review and approval of the documents of that phase to UCOP.  These projects are referred to as "streamlined" projects, although it is more accurate to say that the particular phase as been approved for streamlined processing.

The State Capital Program Office will make every effort to avoid delay to the project in performing this review and release of funds action.  This review will be done concurrent with agency review where possible.

All submissions from the campus to UCOP for streamlined approval should contain all the same components as a submission to DOF.

Streamlined appropriations also have different deadlines for encumbrance and liquidation of funds.  The constraints specific to each appropriation are communicated by the UCOP State Capital Program Office to the campus following the passage of the budget act.  It should be noted that streamlined processing typically is authorized by the State on the basis of campus and University  commitments for accelerated delivery or other aspects regarded as beneficial to the State.  It is important to meet those commitments to support continuance of the program.  Quarterly status reports will continue to be made to the State, and a formal detailed report is required each year.
 

The following pages list the required submittal components for the basic phases of a capital project.  A general description of review criteria for each submittal type is also included.
 

The Following pages list the required
submittal components for the basic 
phases of a capital project. 

A general description of review criteria for each submittal type is also included.

 

REQUIRED SUBMITTAL COMPONENTS
PRELIMINARY PLANS

  1. Cover Letter, 1 original
  2. Request for Approval to Proceed or Encumber Funds, 1 signed original
  3. Capital Outlay Cost, Funding and Schedule Summary, 1 original
  4. Project Description, dated, 1 copy
  5. Preliminary Construction Cost Estimate, dated, 1 copy (including summary sheet and CIB breakdown)
  6. Area Reconciliation, dated, 1 copy (for projects including building space)
  7. Project Schedule, dated, 1 original
  8. Capital Improvement Budget, 1 signed original
  9. Cost Plan Summary, 1 copy
  10. Preliminary Plans, 1 set
  11. Outline Specifications, 1 set

Submittal Format  

  • Clip items 1 through 7 together. Keep items 8 and 9 separate.  Outline specifications should be bound separately. Half size drawings should be submitted if they are legible and easily read.
Identify the project title (as titled in the Regents Budget and the Budget Act ) in the head of the cover letter.


Submittal is reviewed at OP and DOF for:  

Conformity to approved scope and cost defined in the Budget Act, Supplemental language, and approved PPG.
                    Specific items reviewed include:
  • Approved ASF and OGSF
  • Approved programs and space allocations
  • Approved project amenities
  • Approved cost and its allocation within the budget

All variances from approved scope and cost should be noted and explained fully in the cover letter.

Conformity to agreements and policies of the University and State.  Is the project clearly the most cost effective design solution that will meet the requirements of the approved PPG.

Accuracy and Consistency

    • Cost index of estimate (or estimate summary) should match cost index of approved CIB associated with the phase of the project which is being submitted.
    • Consistent asf and ogsf throughout the submittal, i.e. project description, CIB, and area reconciliation.
    • Consistent quantities and qualities of materials indicated in the plans, specifications and cost estimate


REQUIRED SUBMITTAL COMPONENTS
BID PACKAGE (Working Drawings)

  1. Cover Letter, 1 original
  2. Request for Approval to Proceed or Encumber Funds, 1 signed original
  3. Capital Outlay Cost, Funding and Schedule Summary, 1 original
  4. Project description, dated, 1 copy
  5. Construction Cost Estimate, dated, 1 copy (including summary sheet and CIB breakdown) (Bid alternates and their estimated costs to be listed on a separate page)
  6. Area Reconciliation, dated, 1 copy
  7. Project Schedule, dated, 1 original
  8. Capital Improvement Budget, 1 signed original
  9. Cost Plan Summary, 1 copy
  10. Working Drawings, 1 set
  11. Final Specifications, 1 set
     

Submittal Format

Clip items 1 through 7 together. Keep items 8 and 9 separate. Specifications should be bound separately.  Half size drawings should be submitted if they are legible and easily read.

Identify the project title (as titled in the Regents Budget and the Budget Act ) in the head of the cover letter.


Submittal is reviewed at OP and DOF for:  

  • Conformity to approved scope and cost defined in the State approved PPG and supplemental Budget language.

Specific items reviewed include:

  • Approved ASF and OGSF
  • Approved programs and space allocations
  • Approved project amenities
  • Approved cost and its allocation within the budget
  • Any variances from approved PPG and preliminary plans with respect to scope and cost should be noted and explained fully in the cover letter.
Conformity to agreements and policies of the University and State. Is the project clearly the most cost effective design solution that will meet the requirements of the approved PPG?
Accuracy and Consistency
  • Cost index of estimate (or estimate summary) should match cost index of approved CIB associated with the phase of the project which is being submitted.
    Consistent asf and ogsf throughout the submittal
    Consistent quantities and qualities of materials indicated in the plans, specifications and cost estimate


REQUIRED SUBMITTAL COMPONENTS
CONTRACT AWARD

1) Cover Letter, 1 original
2) Request for Approval to Proceed or Encumber Funds, 1 signed original
3) Capital Outlay Cost, Funding and Schedule Summary, 1 original
4) Bid Tabulation, dated, 1 original
5) Project Schedule, dated, 1 original
6) Drawdown Schedule, 1 copy (only needed at contract award submittal)
7) Capital Improvement Budget, 1 signed original

Submittal Format

  • Arrange items 1 through 7 and clip together.
Identify the project title (as titled in the Regents Budget and the Budget Act ) in the head of the cover letter.


Submittal is reviewed at OP and DOF for:

  • Conformity to approved scope and cost defined in the State approved PPG and supplemental Budget language.
Specific items reviewed include:
  • Approved cost and its allocation within the budget
  • Conformity to agreements and policies of the University and State.  Is the project clearly the most cost effective design solution that will meet the requirements of the approved PPG?
Accuracy and Consistency
  • Cost index of estimate should match cost index of approved CIB associated with the phase of the project which is being submitted.
  • Consistent asf and ogsf throughout the submittal
  • Consistent quantities and qualities of materials indicated in the plans, specifications and cost estimate

The following pages provide additional detail with regard to requirements for the various submittal components outlined above.

 

The Following pages provide additional detail with regard to requirements for the various submittal components outlined above.

 

COVER LETTER
 

  • The intent of the cover letter is to assist the UCOP State Capital Program Office in the review of the material and in the preparation of the submittal to the DOF.  Relying on UCOP to "discover" changes or potential issues regarding the submittal is not beneficial to the campus objective of a timely and successful State approval action.
Identify and explain any significant deviations from last approved PPG or submittal with regard to scope, cost, funding or schedule.  In addition describe and explain other items that could be controversial that we should be aware of regarding  Scope, Siting, Utilities, Programmed Uses, Area Reconciliation, Design, Budget, Contracting Method, etc.  Note that the State is no longer approving design-build contracts unless the budget act appropriation authorized it explicitly.
Explain the reasons for the deviations.
List items in the cover letter which are being transmitted in the submittal and the date of each document.
List any work to be bid separately or performed by campus workforce.   Include the estimated cost of the work and be sure that these amounts are included in the Summary of the Cost Estimate and the CIB.
For the working drawing submittal, list in the cover letter any bid alternates to be included with their estimated cost.
Be sure to include the required one page Cost Plan Summary for all new building  construction projects.

Address the letter: Principal Architect Maguire

State Capital Program Development
University of California - Office of the President
1111 Franklin St., 10th Floor
Oakland, CA 94607-5200

CC Director Larry Aull without attachments

REQUEST FOR APPROVAL TO PROCEED OR ENCUMBER FUNDS

This required form, which has been in use by DOF since June of 1998,  will be available on the UCOP Budget Office web site.  Electronic copies are currently available by email from UCOP staff.   "Streamlined" project phases use a version of this form that reflects UCOP rather than State action.

  • Include project CFIS number.
Full project title as it appears in the Regents’ budget.
Date of requested DOF or SPWB action and date of last action
Check all items that apply.
  • If any changes in cost, funding or schedule are proposed then in the last line of item 5. The corresponding word should be made bold and underlined.  Follow this line with a one line description of the change.
Form should be signed and dated by authorized campus representative.
For "streamlined" project phases use the appropriately modified form which has UCOP approval signature line at the bottom of the form.

Any questions regarding this form or the information required on it should be directed to UCOP staff.

CAPITAL OUTLAY COST, FUNDING AND SCHEDULE SUMMARY

This form, which DOF has required since June of 1998,  will be available on the UCOP Budget Office web site.  Electronic copies are currently available by email from UCOP staff.

  • Include project CFIS number.
Full project title as it appears in the Regents' budget.
All information on this form must be consistent with the other documents being submitted; particularly the cost estimate, the CIB, and the schedule.

Any questions regarding this form or the information required on it should be directed to UCOP staff.
 

PROJECT DESCRIPTION
Keep it short, simple, and concise (one-half to one page)

Include the following information:
  • Correct project name (as listed in the Regents Budget).
  • Total current gross and assignable square footage (Note -Be sure that this is consistent with the CIB, Area Reconciliation and Cost Estimate)
     
  • Departments and/or programs being housed with the associated asf as described in the approved PPG
     
  • Types of spaces as identified in the approved PPG (i.e. classrooms, teaching laboratories, research laboratories, faculty and/or administrative offices, support space)
    • A simple and brief physical description of the design solution (Stories, type of construction and proposed materials)

       
    • Location on campus

       
  • Suggestions:
    • Do not repeat the PPG justification, the project has already been justified and funded.

       
    • Do not glorify the physical or aesthetic attributes of the design solution.

       
    • Refer to the project's description in the Regents Budget for simplicity in format.

       
    • Discuss any significant changes in scope, budget or schedule with Office of the President staff to determine if those changes should be addressed in the description.
COST ESTIMATE
  • Provided by the executive architect/engineer or cost consultant and based upon the plans being submitted.
Include a Summary of the Cost Estimate to identify those items not covered in the cost estimate for separate/specialty bids, work performed by campus work forces or direct purchases which are included in the construction costs indicated on the CIB.  Format the summary so that the costs in the estimate and separate contracts match the totals indicated for each of the CIB line items 0, 1, 2, and 4.  The purpose of the summary is to make the connection between the estimate and CIB simple and understandable for a reviewer either at DOF or UCOP.
Identify the CCCI used for the estimate.  If it is different from the CCCI of the CIB which is being submitted, adjust the estimate to the CCCI of the CIB on the Summary of the Cost Estimate.
Both preliminary plans and  working drawing estimate should not rely on "lump sum" or "allowance" categorical estimates.  Normal detailed takeoffs are  expected for estimate items.
Cost estimate should not display an allowance specifically for design contingency.  While it may be prudent to have a design contingency during preliminary plans in normal industry practice, the only identified contingency acceptable to the Legislature is designated in the CIB Line 9 "Contingency" for change orders in construction.
  • Construction costs should be escalated for inflation during construction (typically using the midpoint), based on the current project schedule.
Cost estimate should show separate lines for general contractor overhead and profit.
  • If mechanical and/or electrical consultants are providing their own cost estimate check for consistency to the items listed above.
Do not report $/sf by Specifications Division in the cost estimate summary.  This information should be included only in the Cost Plan Summary.
  • Review the estimate for "Red Flag Items/Verbiage" and make appropriate modifications as needed before sending to OP.
  • Include a separate sheet for cost estimates of alternates.  Estimated costs should be identified in cover letter.
AREA RECONCILIATION
  • An area reconciliation table is required for projects which involve assignable building space.
The preliminary plan submittal should include a table that lists the areas (space type, and total asf per space type) of the project as approved in the PPG or latest amended PPG and the area allocations as currently designed and presented in the submittal.  Do not use the DPP numbers.  Do not include an additional column indicating the difference between the two columns (PPG vs. Preliminary Plans).
The working drawing submittal compares the areas of the project as presented in the preliminary plan submittal, or as authorized in subsequent legislation, to the area presented in the current submittal.  The reconciliation should indicate a breakdown by category of room or function (space type) within each major user group/section, using a list of categories and rooms that is consistent with earlier submittals and the PPG.
Be sure these numbers correspond with the project's description, the CIB, and the cost estimate.
Note any deviations from the last approved submittal in the transmittal/cover letter with a complete explanation so that UCOP can effectively explain the deviation if questioned during State review of the submittal.
PROJECT SCHEDULE
  • Update the schedule to reflect current information.
Date on the schedule should reflect the date of the current submission, even if no other changes are required.
Schedule should be realistic as it is a commitment between the University and the State.  The start and completion dates for each phase are included in the supplemental language of the State Budget Act in which the appropriation was made.
The format and phases/steps identified in the schedule are as defined in the guidelines for preparation of the Project Schedule.

Revenue Bond funded projects should allow approximately six weeks for SPWB approval after the completion of working drawings.  The Bid and Award period should be approximately three to four months long, depending on the length of the bid, to include enough time to submit the bids and request DOF concurrence to award the construction contract.

  • Included during the Working Drawing and/or Agency Review time periods (prior to DOF/SPWB Review) are actions by The Regents, UC General Counsel, DOF and State Treasurer for the Leases (Site and Facility, or Equipment) and Construction (or Equipment) Agreement required for a Revenue Bond funded project.  The campus must submit a Regents Item for the Approval of the Leases and Agreement for the Regents meeting approximately two months prior to when the SPWB action is planned.  The campus must also submit to General Counsel, with a cc to Principal Architect Maguire, a copy of the Legal Description for the property and a Boundary Survey (legal size format please).  The Leases and Agreement must be signed by The Regents prior the SPWB taking action.
  • Do not indicate internal campus processes on the Project Schedule.
CAPITAL IMPROVEMENT BUDGET (CIB)
  • Update last approved CIB to reflect current submittal:
  • CCCI/EPI 
  • Status of the Project
  • Funding Schedule
  • Analytical Data
  • Construction Costs
  • Date
  • Funding Schedule
    • All "prefunded" amounts remain at the actual dollar figure as funded (i.e. don't increase to reflect new CCCI/EPI).

       
    • Current fiscal year request and all future funding requests are calculated at the CCCI/EPI of the current fiscal year as shown on the CIB.
  • Construction Costs
    Construction costs are to be based on the consultant's detailed cost estimate, plus any work bid separately or by campus workforce that has not been included in the consultant's cost estimate.  Examples:  Separate grading contract, telecommunications, asbestos, air balance, direct purchase, etc.

    Present these additional costs and their distribution to CIB lines in a Summary of Cost Estimate to which the consultant's detailed cost estimate is attached.
  • Round to the nearest $1,000
  • Status of Project
    • List current status of project, e.g.:
      • Completion of Preliminary Plans
      • Completion of Working Drawings
      • Award of Construction Contract
  • Analytical Data
    • The top line is for the asf per PPG from the latest approved PPG, PPG Addendum, or Preliminary Plans.  Include the date of the last approved document in parens on the left hand side adjacent to ASF/PPG.

      The second line is for the current submittal's asf.  Be sure the asf matches the asf of the project description and the area reconciliation.

      Under unit costs, the construction cost per asf and ogsf is based on Line 1 Construction only.

      Even if no other changes to the CIB are required, the date should be revised to reflect that the CIB is based on the cost estimate provided with the submittal.


COST PLAN SUMMARY

The Cost Plan Summary is a summary listing of the major estimate categories of the project which includes the following information for each major component system category:

  • unit cost per ogsf excluding contractor’s markup
  • total cost per category excluding contractor’s markup
  • unit cost per ogsf including contractor’s markup
  • total cost per category including contractor’s markup

The Cost Plan Summary should include subtotals of the building component categories separate from costs related to the site.
 

DRAWING SETS
(PRELIMINARY PLANS and WORKING DRAWINGS)

  • Plans submitted should fully describe the project and include all disciplines as applicable (Civil, Architectural, Structural, Electrical, Mechanical, Plumbing, Laboratory, Landscape).  Preliminary plans are design development level documents and should include all disciplines which are related to the project.  The working drawings submittal shall be the final bid document set.
  • Design must conform to the scope and budget delineated in the PPG.
  • Room designations should be consistent with the list defined in the PPG and/or preliminary plans.
  • The design presented should be a cost-effective solution.
  • Suggestions:
    • Review the documents for elements that have been revised or deleted as part of value engineering and be sure there are no conflicts with the PPG.
       
    • The date indicated on the drawings should be identical to the date of the drawings used to prepare the cost estimate.
       
    • Review the landscape drawings for differences in sizes and materials from that indicated in the cost estimate.
    • Indicate the submission status in the title block, i.e. preliminary plans or working drawings.
    • Review the drawings to ensure that the consultant has not indicated a percentage of completion; plans are to be complete and final for that phase.
       
    • Check for "Red Flag Items/Verbiage" also apply here.
    • Working Drawings shall have the State Fire Marshal and the Office of the State Architect stamp and signature.


OUTLINE OR FINAL SPECIFICATIONS
 

  • The specifications should be consistent with the drawings and cost estimate, covering all aspects of the project.
Check for "canned" specifications that include items that are not part of the project.
Include the Instructions to Bidders and the related Boiler Plate.  This material provides information needed by bond counsel (State) for Revenue Bond funded projects.
Include all alternates in working drawings submittal.

State Fire Marshal and Office of the State Architect stamp and signature on final (working drawings) specifications.

 

RED FLAG ITEMS or VERBIAGE
(Unless specifically identified in the approved PPG to meet program needs)

The State, because of budget limitations, only funds projects and items in projects that are demonstrably cost effective in providing the spaces and support for approved program uses.  The following items have in the past caused the State to question the appropriateness of allocating State funds for costs associated with these items.  In some cases these costs have been disallowed and deducted from the project.  Review all submitted documents for the following items and modify the description or the design as necessary avoid raising concerns about appropriate use of State funds.  If the campus wishes to include special items of the types listed in the construction of the project, it should consider doing so with campus funds.

  • Water Features

Large box trees (over 24" box).  The typical tree size approved by the State is 5-gallon.

Excessive landscape area

Landscaped pedestrian malls

Excessive quantity or high cost landscape furnishings or bollards
  • High cost interior or exterior finishes (i.e. wood paneling, decorative metal ceilings, copper roof)
  • High cost applied facade treatments (i.e. premium quality limestone, and other extraneous high cost materials or features applied for aesthetic affect only)
  • Unit kitchens or residential kitchen equipment and use of terms such as  lounge, kitchen and coffee rooms in State-supportable program space.
  • Elaborate skylights and atria
  • Free standing canopies/arcades/towers (attached "arcade" should be called "exterior covered walkway")
  • Balconies, terraces or roof top planters
  • Visiting Scholar or Emeritus offices
  • Commons (Use of label "Lobby" or "Interaction Area" ok if the space was programmed as such)
  • Trellis (If function can be described as a sunscreen for shading/energy conservation purposes, call it a sunscreen)
  • Use of term "extra" for finishes or type of configuration in the cost estimate (just name the finish and $/sf)
  • High cost hand/guard rails (i.e. glass and/or stainless steel)
  • High cost storefront/window system (i.e. teak, mahogany)
  • Use of the terms "custom" or "premium" or "architectural" for fixtures, finishes, or type of configuration in the cost estimate (just name the fixture, finish or configuration followed by the unit cost, the quantity and the total line cost.)
Do not include any Group 2&3 Equipment (any equipment that is not physically attached, hardwired, ducted, plumbed, or permanently made a part of the building, e.g., free standing tables
  • Pedestrian bridges
Special high cost pavements not required by the function of the program


 

 

 